TGC-4 spent $7.8m on energy facilities repairs | Central regions, Energy, utilities MarchmontNews.com

Central regions | Energy, utilities

TGC-4 spent $7.8m on energy facilities repairs

25 Feb '10
Power generating company TGC-4 spent a total of $7.8m on energy facilities repairs in Voronezh region in 2009, the company reports.

The funds were reportedly used to repair 14 energy boiler houses with total steam producing capacity of 2,035 tons per hour, eight turbine units with total power capacity of 180 MW, as well as 14 water heaters with heating capacity of 1,230 GCal per hour.

The funds were also spent to replace 15.5 kilometers of heat mains and overhaul 3.3 kilometers of heat mains.